The Project

Blairgowrie residents in Zone 2 overwhelmingly voted in favour of applying for fenced off road closures and boom gates. More than two-thirds of residents approved the proposal in early 2024.


We are currently engaging the City of Johannesburg in this regard and acquiring all the necessary reports to be compliant. 


The Nola Park Community Road Closure project has established a Non-Profit Organisation to be the legal entity overseeing the project which is being guided by a resident and attorney specialising in road closures. You can sign up to become a voting member of the Nola Park Community NPC by completing the membership form below.

To support the project residents have been asked to contribute R300 a month towards financing the costs involved. If you are not yet contributing, please click below for the banking details.

We have submitted our application to the City of Joburg and are waiting for their interim decision.

The Process

Pre Submission Phase

Started in June 2024
Completed October 2025
    • Confirm support from 2/3 of residents
    • Registered Nola Park Community as a legal entity
    • Start collecting contributions from residents
    • Traffic Impact Study by a traffic engineer – R68000
    • Tender and vote for infrastructure and security company
    • Members of Nola Park Community NPC commit to monthly contributions of R300
    • Attorney compiled application for City of Joburg

Application
Phase

Started in October 2025
+/- 10 months
  • Submitted application to City of Joburg – R39000
  • Submit any outstanding documentation requested by COJ
  • Meeting, discussion with COJ

    NEXT STEP

  • Waiting for interim decision from COJ - currently 70 days overdue
  •  advertised to community for public comment – R22000
  • If no commentary COJ provides final decision on application
  • Final decision advertised in Government Gazette
  • Date of implementation provided


Construction Phase

4 Months
  • Final decision on security company to partner with on road closure
  • Final decision on construction company and infrastructure specifics
  • Wayleave (permission to work on the road) application to COJ
  • Construction MUST be finalised within 4 months of implementation
    This will likely be staggered due to finances
    • Fences, gates, booms, signage – R470 000
    • Cameras – R322 000

Implementation Phase

Ongoing
  • Implementation of road closure security plan
  • Continued collection of committed contributions from community
  • Payment of service providers (security company, insurers)
  • Maintenance of structures

Renewal
Phase

Every 2-4 Years
  • Similar to the application process
  • Submitted at least 1 month before expiry of the approval period